How to Read an RFP: Instructions, Evaluation Criteria and Amendments
A request for proposals can run long, but three parts deserve most of your attention: the instructions, the evaluation criteria and the amendments. Here is where to find each one in a federal or Mississippi solicitation, the order to read them in, and what to write down as you go.
First, know what kind of solicitation you have
GSA lists four common types: a request for proposals (RFP), a request for quotes (RFQ), a sealed bid or invitation for bids (IFB), and a sources sought notice or request for information (RFI). GSA calls the last one a market research tool, so it is not asking for an offer yet. This article focuses on RFPs.
Find the map before you read
Most federal RFPs follow the uniform contract format in FAR 15.204-1. It splits the document into four parts and thirteen sections, A through M. These matter most:
| Section | Title in the FAR | Why you read it |
|---|---|---|
| B | Supplies or services and prices/costs | What you are pricing, line by line |
| C | Description/specifications/statement of work | The work itself |
| F | Deliveries or performance | Dates and places |
| H | Special contract requirements | Terms written for this job |
| J | List of attachments | Drawings, forms and exhibits you must open |
| K | Representations, certifications, and other statements of offerors or respondents | What you certify |
| L | Instructions, conditions, and notices to offerors or respondents | How to prepare and submit |
| M | Evaluation factors for award | How you will be scored |
Not every solicitation looks like this:
- Construction. FAR 15.204 says construction and architect-engineer contracts need not use this format. Construction solicitations expected to exceed the simplified acquisition threshold use Standard Form 1442 instead (FAR 36.701).
- Commercial products and services. These are usually built on Standard Form 1449 (FAR 12.303). The instructions sit in provision 52.212-1 and any addendum to it. The evaluation factors sit in 52.212-2, when the buyer uses evaluation factors. Read any addendum as closely as the provision it belongs to.
- Agencies using the rewritten Part 15. Under the FAR Overhaul, many agencies, including the Department of Defense, NASA and HUD, now follow a rewritten FAR Part 15 through class deviations. GSA's took effect November 3, 2025. Section numbers moved (the uniform contract format is now at 15.109), but Section L still holds the instructions, including how to submit, and Section M the evaluation factors.
Whatever the layout, find where the buyer explains how to submit and how it will judge.
The order to read in
- The first page. Note the solicitation number, the due date and time, where and how to deliver, and the point of contact. GSA's advice is blunt: "In most cases, the government will not accept a late proposal."
- The instructions (Section L, or 52.212-1 and its addendum). FAR 15.204-5 says Section L can require a specific format or separate parts, such as administrative, management, technical, past performance and cost or pricing. This is where you learn how the proposal must be organized and formatted. The standard instructions to offerors in FAR 52.215-1 also say what the first page of your proposal must show.
- The evaluation criteria (Section M, or 52.212-2). Read this before you write a word. It tells you what earns credit.
- The work (Section C) and the price schedule (Section B). Read them with the evaluation criteria in mind, then Sections F and H and every attachment listed in Section J.
- The representations and certifications (Section K). Check that you can truthfully sign each one.
As you go, copy every "shall" and "must" into a list, with the section and page number next to it. That list becomes your compliance matrix.
How to read the evaluation criteria
FAR 15.304 requires the solicitation to state clearly all factors and significant subfactors that will affect award, and their relative importance. It must also say whether all the factors other than price, combined, are:
- significantly more important than price,
- approximately equal to price, or
- significantly less important than price.
That one sentence tells you where to spend your effort. The same section says price or cost is evaluated in every source selection, and past performance is evaluated in all negotiated competitive acquisitions unless the contracting officer documents why it isn't appropriate. The rating method need not be disclosed.
Next, work out which kind of award it is:
- Tradeoff. FAR 15.101-1 allows award to other than the lowest-priced offeror when that is in the government's best interest. Here, strengths you can prove can be worth paying for, so show them.
- Lowest price technically acceptable (LPTA). Under FAR 15.101-2, award goes to the lowest evaluated price among proposals that meet the acceptability standards. Tradeoffs are not permitted, and proposals are evaluated for acceptability but not ranked on the non-price factors. Going beyond the standards earns no extra credit. Meet every one, then sharpen your price.
Also look for a line saying the government intends to award without discussions. FAR 52.215-1 says that in that case, your initial proposal should contain your best terms. Don't hold anything back for a later round.
Mississippi state RFPs
Mississippi state agencies buying non-IT personal and professional services follow the Office of Personal Service Contract Review rules (Title 12, Part 9, effective September 6, 2024). Under those rules, an agency needs approval from the Public Procurement Review Board (PPRB) to use an RFP. Proposals are scored on factors beyond price, such as technical or management factors, and award goes to the offeror with the highest score under the weighted criteria in the RFP.
One rule is worth knowing before you price: price must receive at least 35% of the available points and must be the highest weighted individual factor. Find the points table in the RFP and build your response around it.
These rules list exceptions, including IT services handled by ITS, the Mississippi Department of Transportation and the state universities. So always read the evaluation section of the solicitation in front of you. For where state and local bids are posted, see our guide to finding government contracts in Mississippi.
Questions and amendments
If something is unclear, ask the named contact in writing, before any deadline for questions. Expect your answer to be shared. FAR 15.201 says that when specific information needed to prepare proposals is given to one or more potential offerors, it must be made public as soon as practicable, to avoid an unfair advantage.
When the government changes its requirements or terms, FAR 15.206 says the contracting officer must amend the solicitation. Before the closing date, the amendment goes to everyone who received the solicitation. Each amendment should show at least its number and date, a description of the change, a point of contact and any revised closing date.
Then do three things with every amendment:
- Acknowledge it. FAR 52.215-1 says offerors must acknowledge receipt of any amendment by the date and time it specifies.
- Re-read what it touches. A change to Section L, M or C can change your page count, your approach or your price. Update your compliance list.
- Don't miss the next one. GSA advises signing up to be notified of any amendments, additions to, or communications related to the solicitation. Check again the day before you submit.
Our article on why bids get rejected covers what happens when an amendment goes unacknowledged.
A one-page reading checklist
- Type of solicitation, number, due date and time, delivery method and point of contact.
- Volumes, page limits and format rules from the instructions.
- Every evaluation factor and subfactor, in order of importance, and how the non-price factors compare with price.
- Tradeoff or lowest price technically acceptable, and whether award may be made without discussions.
- Every attachment, form, representation and certification.
- The deadline for questions, and every amendment, acknowledged.
If you'd like help, we write complete, compliance-checked bid proposals for small contractors, and our bid review checks your draft against every requirement in the solicitation before you submit. You can also see how we lay out a response in this sample proposal excerpt.
Websites and rules change. We checked every link and figure in this article on October 28, 2026. If you are relying on a detail for a bid, confirm it on the official page linked below.
Sources
- GSA: Research active solicitations
- GSA: Respond to a solicitation
- Acquisition.gov: FAR 15.204, Contract format
- Acquisition.gov: FAR 15.204-1, Uniform contract format
- Acquisition.gov: FAR 15.204-5, Part IV, Representations and Instructions
- Acquisition.gov: FAR 36.701, Standard and optional forms for construction contracting
- Acquisition.gov: FAR 12.303, Contract format (commercial products and services)
- Acquisition.gov: FAR 52.212-2, Evaluation, Commercial Products and Commercial Services
- Acquisition.gov: FAR Overhaul, FAR Part Deviation Guidance
- Acquisition.gov: FAR Overhaul, Part 15
- GSA: Class Deviation RFO-2025-15, FAR Part 15
- Acquisition.gov: FAR 15.304, Evaluation factors and significant subfactors
- Acquisition.gov: FAR Subpart 15.1, Source Selection Processes and Techniques
- Acquisition.gov: FAR 52.215-1, Instructions to Offerors, Competitive Acquisition
- Mississippi Secretary of State: Office of Personal Service Contract Review Rules and Regulations, Title 12, Part 9 (PDF)
- Acquisition.gov: FAR 15.201, Exchanges with industry before receipt of proposals
- Acquisition.gov: FAR 15.206, Amending the solicitation